Completed projects, explained technically.

For each project: the starting point, the engineering decisions and the result. Including what did not go smoothly.

Location
Eindhoven, Stratum
Property type
1930s Townhouse
Timeline
8 Weeks
Scope
All-Electric Transition + Ground Floor Extension
After
Before
Technical detail
  • 14-circuit consumer unit with separated RCDs
  • Two structural steel beams, calculated and certified
  • Underfloor heating across 6 zones, copper manifold

The challenge

The house still ran on a single-phase supply with six circuits dating from the 1970s. Induction cooking, an EV charger and a heat pump could not coexist. The crawl space was persistently damp, which would have made underfloor heating pointless without intervention.

Technical execution

Supply upgraded to 3x25A with the grid operator, a new NEN 1010 consumer unit with 14 circuits and separate RCDs per function. The crawl space was sealed with a vapour-retarding membrane before the underfloor manifolds were set. The 18 m2 extension is carried on two structural steel beams.

We had quotes from four companies and none of them wanted to own the whole thing. Here one company signed for the entire chain.
MartijnStratumElectricalStructuralClimate
Location
Amsterdam, Oud-West
Property type
1908 Upper Apartment, VvE
Timeline
6 Weeks
Scope
Hybrid Heat Pump, Underfloor Heating and Custom Storage Wall
After
Before
Technical detail
  • Hybrid setup with a noise measurement filed for the association
  • 22 mm low-build underfloor heating
  • Oak storage wall with a concealed services shaft

The challenge

An apartment inside a VvE (owners association) with restrictions on facade units and strict noise limits. The owners wanted to leave gas behind without touching the listed front facade, and without raising floor height by more than 30 mm.

Technical execution

The outdoor unit sits on vibration dampers behind the roof structure, out of sight from the street and inside the association noise limit. A 22 mm low-build underfloor system was combined with a hybrid setup, so the existing radiators can assist on the coldest days.

The association application and the noise measurement were handled for us. That was exactly the part we were dreading.
SanneOud-WestClimateJoineryVvE process
Location
Utrecht, Tuinwijk
Property type
1950s Family Home
Timeline
11 Weeks
Scope
Full Turnkey Remodel, Load-Bearing Wall Removal and Bespoke Interior
After
Before
Technical detail
  • HEA beam with new bearing points and foundations
  • Phase-based payment schedule for the lender
  • Kitchen island with fully concealed services

The challenge

The ground floor was four small rooms around a load-bearing central wall. The owners were relocating from abroad and could not visit the site weekly. Financing ran through a bouwdepot, which required itemized pricing per build phase.

Technical execution

The central wall was replaced with an HEA beam on new foundations under the bearing points, structurally calculated and certified. The ground floor was replanned around an island with all services concealed. A weekly photo log and a shared payment schedule kept both the bank and the owners in the loop.

We were still in London when the wall came out. Every Friday the progress was in the portal with photographs.
ElenaTuinwijkStructuralFull remodelRenovation fund
Next step

An itemized quote, not a ballpark figure.

Four short steps. You receive a scope document your mortgage lender can assess straight away.

Request Scope Estimate

Prefer to talk it through first? +31 613 005 001